The national installed power generation capacity has increased by 10.9%, but why has the average utilization hours decreased by 214 hours instead?

BT财经2026-11-26 12:04
With the expansion of installed power capacity, the core focus of the power industry has shifted to the realization of electricity value.

On November 25, the National Energy Administration released the latest power statistics: by the end of October, the national installed power generation capacity reached 4.16 billion kilowatts, a year-on-year increase of 10.9%; in the first 10 months of this year, the cumulative average utilization of power generation equipment was 2406 hours, 214 hours less than the same period of the previous year.

While power generation capacity is expanding, the average power generation time per unit of equipment is shortening. This set of data is not contradictory, but reveals a noteworthy change in the power industry: as more and more power generation equipment is put into use, whether the generated electricity can be sold, at what time it is sold, and at what price it is finally settled, are becoming important variables that determine the return on investment of power stations.

For power equipment manufacturers, energy investors and power-consuming enterprises, what really needs to be studied is no longer just how many more power stations need to be built across the country, but how the newly added power generation capacity can be converted into electricity that has clear demand, reasonable pricing and guaranteed payment recovery.

Installed capacity and power generation are essentially two separate sets of accounts

First, clarify two units. Kilowatt is a unit of power, representing the power generation capacity of equipment under specific conditions; kilowatt-hour is the unit of electricity volume, which is commonly known as "degree" in daily life. A generator with a rated power of 1000 kilowatts can generate 1000 kilowatt-hours of electricity if it runs continuously at the rated power for one hour.

The average utilization hours of power generation equipment is not the actual running time of the machine, but the equivalent time converted from the power generation volume in the reporting period to the operation of the equipment according to the rated capacity. Assuming that a 1000-kilowatt equipment runs continuously at 500 kilowatts for two hours, its power generation volume is still 1000 kilowatt-hours, and the converted utilization hours is one hour.

The denominator of this indicator is the average equipment capacity in the reporting period within the corresponding statistical scope, not the installed capacity at the end of the period. A power station that was just put into operation at the end of October can be included in the end-of-period installed capacity statistics, but it did not participate in power generation in the previous nine months. Therefore, it is not possible to directly multiply 4.16 billion kilowatts by 2406 hours to calculate the actual national power generation volume in the first 10 months.

Calculated backwards from the figures released by the National Energy Administration, the cumulative average utilization hours in the same period of the previous year was 2620 hours, a decrease of about 8.2% this year. It reflects the change in output per unit capacity under the corresponding statistical caliber, which is affected by both the composition of power sources and the operating status of various power sources. It does not mean that the technical efficiency of generators has decreased, nor can it be inferred that the national power generation volume has decreased by 8.2%.

For an investment project, installed capacity represents the scale of assets, power generation volume represents output, and the actual grid-connected or self-used power volume further forms sales revenue or saved power purchase expenditure. These layers of indicators cannot be confused.

Wind power and solar power are reshaping the entire power source structure

Which part of the 4.16 billion kilowatts of installed capacity is growing the fastest? Data from the National Energy Administration shows that the installed solar power capacity is about 1.33 billion kilowatts, a year-on-year increase of 16.3%; the installed wind power capacity is about 710 million kilowatts, a year-on-year increase of 20%. Estimated based on the published rounded data, the total installed capacity of the two types of power sources is about 2.04 billion kilowatts, accounting for about 49% of the national total installed capacity.

More and more newly added capacity comes from fluctuating and intermittent wind power and photovoltaic power. Photovoltaic power basically does not generate electricity at night, and the output of wind power is affected by changes in wind speed; thermal power can adjust its output within a certain range according to dispatching needs, and nuclear power usually undertakes relatively stable power generation tasks. The typical utilization hours of different power sources are inherently different.

Look at it with a simplified model. Assume that a region originally has 1 million kilowatts of power generation equipment, with an average annual utilization of 4000 hours, and the annual power generation volume is 4 billion kilowatt-hours; add 500,000 kilowatts of new equipment, assuming an annual utilization of 1500 hours, it will generate an additional 750 million kilowatt-hours of electricity.

Under the condition that the output of the original equipment remains unchanged, the total installed capacity increases by 50%, the total power volume increases by 18.75%, but the total average utilization hours change from 4000 hours to about 3167 hours. Without any equipment failure, and there is no need to assume that power curtailment occurs, the average value will drop.

This is an example of structural changes affecting the average value, not a quantitative attribution of the 214-hour national decline. To measure the real contribution, it is necessary to obtain the average capacity of each power source under the same statistical caliber, sub-item utilization hours and simultaneous operating data. The national total alone cannot answer how much of the decline comes from structural changes, and how much comes from demand, weather or dispatching.

Power demand is still growing, but it is not the same at every moment

Observing the supply-side data from the demand side will get another layer of information. The power consumption analysis released by the National Energy Administration on November 24 shows that the total social power consumption in the first 10 months of this year was 8944.2 billion kilowatt-hours, a year-on-year increase of 3.7%. Data released by the National Bureau of Statistics on November 16 shows that the power generation of industrial enterprises above designated size in the same period was 8290.4 billion kilowatt-hours, a year-on-year increase of 1.8%.

The two statistics respectively cover power consumption and industrial power production of enterprises above designated size, and their coverage scopes are different. The two absolute values cannot be directly subtracted to judge the power shortage. But they both remind us that observing the power industry cannot only focus on the growth rate of installed capacity.

Moreover, power consumption is not a flat curve. Factory shifts, business facility opening hours, summer air conditioning and winter heating will all cause power demand to change on different dates and time periods. A certain place may have sufficient photovoltaic power at noon, but after nightfall, other power sources or energy storage are needed for continuous supply. Even if the total annual power volume is sufficient, the problem of reliable power supply during peak hours must be solved.

The operating data for the first three quarters released by the National Energy Administration on October 30 shows that the power generation of renewable energy reached 3.13 trillion kilowatt-hours, accounting for about 41.8% of the total power generation; among them, the combined power generation of wind power and photovoltaic power was about 1.92 trillion kilowatt-hours, a year-on-year increase of 11%. The electricity generated by new energy is increasing, and its power supply contribution should not be denied only by the change of average utilization hours.

The utilization rates of wind power and photovoltaic power in the first three quarters released at the same press conference were 92.1% and 93.1% respectively. These two percentages are not the same indicator as the average utilization hours of power generation equipment: the former focuses on the utilization degree of available power generation, while the latter measures the output per unit of equipment capacity. To judge the power consumption and absorption status, it is necessary to refer to the actual data of the corresponding region, time and power source type.

For a 100 MW power station, what does 200 hours less power generation mean

For power station operators, utilization hours will eventually be included in the financial model. Assume that a 100 MW new energy power station that has been in full operation for one year adopts 1800 annual utilization hours in investment calculation, and the expected annual power generation volume is 180 million kilowatt-hours. If the actual utilization hours are only 1600 hours, the annual power generation volume will become 160 million kilowatt-hours.

Under the assumption that all generated electricity can be connected to the grid, the average settlement electricity price is fixed at 0.30 yuan per kilowatt-hour and other conditions remain unchanged, the corresponding electricity fee income under the two scenarios is 54 million yuan and 48 million yuan respectively, with a difference of 6 million yuan. This example is only a sensitivity calculation, and does not represent the national average electricity price or the operating results of any real power station.

After the power station is completed, depreciation, part of operation and maintenance expenditure, financing cost and other items will not decrease proportionally just because a few degrees less electricity is generated. When the power generation volume and salable power volume of the project are lower than expected, the fixed cost allocated per unit of electricity may rise, and the operating cash flow will also be affected.

At the same time, there is a second variable for power stations: electricity price. Even if the annual electricity sold is 160 million kilowatt-hours, a difference of 3 cents per kilowatt-hour in the average settlement electricity price will lead to a difference of 4.8 million yuan in annual electricity fee income. In actual operation, self-consumption electricity of the power plant, transaction settlement, mechanism price difference, operation and maintenance expenditure, taxes and other items need to be considered, so electricity fee income is not equal to net profit.

The document No. FGJG [2025] No.136 issued by the National Development and Reform Commission and the National Energy Administration in 2025 requires that the grid-connected electricity of wind power and solar power generation shall in principle enter the power market, and the grid-connected electricity price shall be formed through transactions, and a settlement mechanism for price difference outside the market shall be set for eligible electricity, with classified treatment for existing and new projects.

This means that power station investment calculation cannot only multiply the unified electricity price by the designed power generation volume. Enterprises also need to estimate the electricity volume and electricity price in different trading periods, the electricity volume included in the mechanism, price difference settlement and contract risks respectively according to the local implementation plan, and then calculate the debt solvency and payback period.

Power grid, energy storage and dispatching: business value is realized through actual operation

After the expansion of power generation capacity, whether electricity can match demand across time and regions is related to whether the equipment investment can give full play to its value. Power transmission channels are responsible for transmitting surplus power to other load centers, energy storage can be charged at appropriate time periods and discharged when needed, and load management can guide eligible power-consuming enterprises to adjust their power consumption time.

These capabilities are not the same type of commodity. Power transmission business focuses on the construction, operation and transmission capacity of lines and transformation equipment; energy storage projects focus on available capacity, charge and discharge efficiency, dispatching frequency and revenue mechanism; power digital services need to connect forecasting, planning, transaction and actual operation data.

The National Energy Administration disclosed on October 30 that by the end of September, the scale of new-type energy storage put into operation across the country reached 167 million kilowatts and 435 million kilowatt-hours, with an average energy storage duration of about 2.61 hours. The former describes the power that can be provided, and the latter describes the energy that can be stored. Both indicators are important, and energy storage installed capacity cannot be directly regarded as a power source that can generate electricity continuously forever.

Energy storage cannot make profits simply by relying on the price difference between peak and valley electricity. The project must calculate the power purchase cost for charging, income from discharging, conversion loss, battery attenuation, maintenance and capital cost, and also judge whether there are corresponding auxiliary services or other revenue mechanisms in the local area. How much effective dispatching is available after the equipment is completed and whether the provided services can be settled determine the actual return.

The power market also provides tools for resource allocation. The cross-provincial and cross-regional transaction power volume in the first three quarters announced by the National Energy Administration was 1303.7 billion kilowatt-hours, a year-on-year increase of 9.1%. This does not mean that every transaction is new energy power, but it shows that expanding the transaction scope has a practical foundation for supply and demand matching. The opportunities in the future are not only to manufacture more equipment, but also to improve the effective output and operation value of existing equipment.

To judge the value of power investment, we cannot only focus on the installed capacity ranking list

From the perspective of the industrial chain, power generation equipment manufacturers pay attention to orders, delivery and operation and maintenance services; power station operators pay attention to salable power volume and actual settlement price; industrial and commercial users pay attention to their own power consumption curve, power supply reliability and comprehensive electricity cost. The indicators required by the three parties are not the same.

To analyze the power industry in the next stage, we must first track the installed capacity and actual power generation of different power sources, then look at the regional power absorption status, utilization hours and power grid regulation capacity, and then observe the transaction electricity price and project cash flow. Especially for power station projects, local resource conditions, actual grid connection arrangements and applicable transaction rules must be adopted, instead of taking the national average as the revenue forecast.

The figure of 4.16 billion kilowatts shows that China's power supply capacity is expanding; the 214-hour reduction reminds the market that it is necessary to understand how each unit of capacity participates in production. With the increase of the proportion of new energy, the operation issues of the power industry are extending from simply expanding the scale of power generation to the coordination of power generation, transmission, regulation, transaction and settlement.

For enterprises, to measure the value of a power investment, the final judgment is not only how many kilowatts of equipment have been completed, but also how much electricity these equipment can provide when needed, and how much value they can create in a sustainable commercial way.