Is the pioneer of floating wind power on the verge of bankruptcy? It holds patents and possesses relevant technologies, only to end up being sold off at a fire sale for a mere 1 pound.
Pioneer of floating wind power Hexicon exits with its asset-light model, while heavy-asset players take over
On November 6, the board of directors of Swedish firm Hexicon signed a balance sheet prepared for liquidation, leaving the decision on whether the company will continue operations to an extraordinary general meeting of shareholders scheduled for November 25.
Founded in 2009, the company that first commercialized the twin-turbine floater had 880 million Swedish kronor in shareholder equity on its books, yet KPMG (one of the Big Four global accounting firms) refused to sign off on the statement. Back in April this year, it sold TwinHub, England's first floating wind project to secure a Contract for Difference, for a nominal consideration of 1 pound, transferring all its equity and liabilities related to the project.
The asset-light business model of "nurturing projects and selling patents" has been ruled unviable in deep offshore waters: the total planned capacity of floating wind projects across countries amounts to 152GW, while only 382MW has been put into actual operation; the publicly announced global floating wind target exceeds 90GW, but merely 1.5GW has signed power purchase agreements.
What is lacking is not design drawings, but balance sheets that can afford to submerge steel structures to water depths of 50 meters and withstand years of no positive returns.
One Pound, One Krona
Swedish company law has a procedure called the "control balance sheet": if there is suspicion that half of the company's own capital has been eroded, the board of directors must prepare such a statement for auditors to review, and then submit it to the general meeting of shareholders to decide whether to close the business.
The shareholder equity stated on Hexicon's balance sheet is 880.7 million kronor, while its registered share capital is only 3.64 million kronor, which is far below the warning line. The problem lies in KPMG's refusal to sign, citing significant uncertainties in financing and going concern, and insufficient audit evidence to support the revaluation of fixed financial assets. A "disclaimer of opinion" in accounting terms means the accounting firm does not endorse these figures.
The board of directors lists continuing operations as the primary plan, while acknowledging that short-term financing "has not yet been secured"; if liquidation does happen, the official announcement has clearly stated that shareholders should not expect to get any money back from distribution.
The capital market cast a vote of no confidence two years earlier than the auditors: the closing price on November 6 was 0.1115 kronor, with a market value of about 40.56 million kronor, down 35.4% in one year. The company has only 11 employees but operates across Europe, Africa and Asia, meaning each person is in charge of a whole continent. With 880 million kronor recorded on the books, the market only values the company at 40 million kronor, a 20-fold gap.
What it has been selling is never electricity. Its revenue in the second quarter of 2026 was 1.3 million kronor, compared with 5.2 million kronor in the same period last year; it posted an operating loss of 12.5 million kronor, and negative operating cash flow of 9.4 million kronor. Its revenue came from nurturing projects to a semi-mature stage before reselling them, and its assets came from revaluation of facilities that had not yet been completed. Once the auditor withdrew its endorsement, the paper value collapsed completely.
The Day After the Ban
After the UK ban came into effect in March, there were market rumors that a Chinese enterprise was involved in the 1-pound transaction. After checking all the announcements, the buyer turned out to be Singaporean offshore engineering enterprise Seatrium, who did not disclose its name in April and only confirmed the acquisition at its half-year performance meeting on July 31; the only thing related to China was the unfulfilled wind turbine order placed two years ago.
This mismatch itself is newsworthy: the pioneer's project site was taken over by an enterprise with its own shipyard, while Chinese wind turbines that were originally most likely to reduce costs were blocked outside the market. Chris Ong, CEO of Seatrium, said that the purpose of acquiring this site is to "enter the market in advance and get a platform to verify our technology and supply chain".
The rules have changed. Sweden rejected 11 out of 13 submitted applications on the grounds of "unacceptable impact on national defense capabilities"; the UK set the maximum strike price for floating wind in AR8 at 271 pounds per MWh, compared with 113 pounds per MWh for fixed-bottom wind (2024 prices), and requires all bidding projects to obtain Grid Gate 2 access qualification first.
Policies no longer reward early movers, they redistribute the game rules based on nationality, national defense and deliverability. The intermediate technical licensing parties are the most affected: they have neither stable electricity price as a safety net, nor the ability to complete the project construction on their own. Their supply chains are divided by political factors, and even switching suppliers becomes extremely difficult.
At present, the maximum price the government is willing to pay for floating wind power is 2.4 times that of fixed-bottom wind power. The results will be announced as early as November 27, two days after Hexicon's shareholders' meeting. Schumpeter called innovation "creative destruction", and this round of destruction has precisely fallen on the earliest innovator.
Whoever Has the Vessels Calls the Shots
Seatrium, the acquirer, owns shipyards and holds a net order book of SGD 13.3 billion, and regards floating wind power as an opportunity pool worth about SGD 9 billion. It paid 1 pound for TwinHub to obtain a test site where turbines can be actually deployed, grid connection and operation and maintenance processes can be verified, to validate its self-developed FWSS semi-submersible foundation, which is designed for 15MW units and has obtained DNV's approval in principle and ABS's basic design approval. What it bought is the sea area, permits and market access ticket, not Hexicon's TwinWind technology.
Chinese enterprises have already put the same twin-turbine design into operation to generate electricity at sea. On December 11, 2024, the "Mingyang Tiancheng" unit was put into operation at Yangjiang Qingzhou IV wind farm, with two 8.3MW wind turbines installed on one single floater, totaling 16.6MW. The site is about 70 kilometers offshore with a water depth of 45 meters, generating about 54 million kWh of electricity annually. It was developed by a wind turbine OEM that has manufacturing capabilities, project resources and power offtake channels; Hexicon's role was limited to project incubation and technology licensing, and its floaters had to be manufactured by third parties.
The high cost of floating wind power becomes clearer when broken down: DNV estimated in its *2026 Energy Transition Outlook* that the levelized cost of electricity for floating wind ranges from 350 to 450 USD/MWh, compared with about 113 USD/MWh for fixed-bottom wind; the levelized cost of electricity spreads all expenses from construction, operation and maintenance to decommissioning across every kWh generated over the project's entire lifecycle. The cost gap comes from steel, anchor chains and vessel scheduling: to manufacture, tow and secure the floaters, you need shipyards, docks and sufficient production capacity, not just patent certificates.
DNV judges that large-scale installed capacity of floating wind will not arrive until the 2040s. The port upgrades in Scottish ports carried out under the government's 500 million pound plan are now facing the risk of becoming stranded assets, as operators worry that no orders will come in. The UK's Carbon Trust predicted in 2015 that global floating wind installed capacity would reach 5.5GW by 2025, but the actual figure is only 382MW, completing merely 7% of the target.
Not all technology licensing players failed: BW Ideol, which develops the Damping Pool foundation, is backed by shipowner BW Offshore. In 2023, it received 40 million euros of development funding from the French Ecological Transition Agency, and then obtained a 12 million euro shareholder loan, before pushing forward a floater production line with an annual output of about 1GW in Port-la-Nouvelle.
Its then CEO Paul de la Guérivière positioned the company as "a technology and EPCI provider, as well as a wind farm developer and co-owner". The difference does not lie in the technical route, but in who can survive the years with no revenue.
The twin-turbine design did not lose. What failed was the people who thought they could collect rent forever just by drawing design drawings. In this industry, the least valuable thing is the first-mover advantage, while what really counts are vessels, shipyards, and cash flow that can sustain operations until the project is connected to the grid.
At the November 25 meeting, the board of directors listed continuing operations as the primary plan, but financing has not yet been secured; even if shareholders agree to continue operations, another meeting must be held within eight months to review the liquidation proposal. In the same week, the UK AR8 auction results are likely to be released, with the floating wind price cap set at 271 pounds. TwinHub is eligible to participate in the auction, with Seatrium as the applicant, using its own self-developed foundation.
The 880 million kronor is still recorded on the paper, but the sea area, permits, grid access channels and the access ticket for the next round of auction have all been transferred to new owners. On the day of the 1-pound transaction, Hexicon no longer had the right to decide what type of floater to install at the TwinHub project.